Quick Root Cause Record

_NCMR-compatible nonconformance record_

NC Description

Cold solder / insufficient wetting on QFN-48 ground-pad thermal via array joints on BCN-IoT-4800 Rev C, produced on Reflow Oven #1913, against the internal target of <0.5% defect rate (IPC-A-610 / J-STD-001, Class 2). Detected by routine AOI (Dan Kim), confirmed by X-ray. First detected June 2, 2026.

NC owner: Anna Novak, SMT Process Engineer (CAPA owner, NCR#26-0244).

Scope / Quantity at Risk

Disposition

Containment

ActionStatusOwner
100% X-ray screening of all Oven #1913 output, affected PN, June 2–10CompleteDan Kim
84 confirmed defective joints reworked and re-inspected (X-ray + AOI)CompleteRework: Raj Patel / Re-inspection: Dan Kim
New-build WIP on Oven #1913, affected PN, halted and diverted to #1911/#1912In placeLinda Chen
Oven #1913 taken out of service for affected-PN new buildsIn placeRaj Patel
Traceability pulled — paste lots, board lots, oven profile changes, last 8 daysCompleteAnna Novak
Customer complaint queue reviewed — no escapes confirmedCompleteDan Kim

Verification: 100% X-ray screening confirms no unscreened product has shipped or can ship from the suspect population. No customer notification or regulatory report required — Class 2, no safety-critical application, zero field exposure, no customer complaints as of June 10, 2026.

Decisive Contrasts (IS / IS-NOT)

DimensionISIS NOT
Defect typeCold solder / insufficient wettingBridging, opens, tombstoning, voiding, head-in-pillow
Component / locationQFN-48 ground-pad thermal via array joints onlyAll other component types and joint types on same boards
EquipmentReflow Oven #1913Ovens #1911, #1912
ZoneZone 7 (peak/reflow zone, ~5°C below setpoint)All other zones on #1913; all zones on #1911/#1912
When — startJune 2, 2026 (day after paste lot PST-26-0339 introduction)Before June 2, 2026 — #1913 at expected yield prior
Paste lotPST-26-0339 present on all three ovens in windowPaste lot unique to #1913 — same lot ran clean on #1911/#1912
Defect rate4.2% on #19130.3% on #1911/#1912 (same paste lot, same window)

Decisive contrasts:

1. Same paste lot ran on all three ovens, but defects appeared only on #1913 — this rules out paste lot alone as the cause and points to something oven-specific.

2. Zone 7 is the peak/reflow zone, the exact point in the profile where the board must cross liquidus — a shortfall there hits hardest at the highest-thermal-mass joint.

3. Defects are isolated to the QFN ground pad only, not distributed across joint types — consistent with a marginal, not gross, thermal shortfall that only bites the joint with the least margin.

6M Fishbone (breadth)

Machine

Material

Method

Measurement

Man (People)

Environment (Mother Nature)

5-Why Chain

Why 1: Why did the QFN-48 ground-pad thermal via array joints exhibit insufficient wetting on Oven #1913?

> The joint did not reach or sustain sufficient temperature above liquidus during reflow.

> Evidence: Zone 7 thermocouple history log; COA liquidus 219°C; defect isolated to highest thermal mass joint.

Why 2: Why did the joint not reach sufficient temperature above liquidus?

> Zone 7 (peak zone) ran ~5°C below setpoint (RC-1) at the same time paste lot PST-26-0339 required 2°C more thermal energy to wet (RC-2, liquidus 219°C vs. 217°C standard). The QFN ground pad — slowest joint to heat — was the only location where the combined margin loss crossed the wetting threshold.

> Evidence: Zone 7 thermocouple history log; COA PST-26-0339; COA standard lot; defect isolated to QFN ground pad only, all other joints wetting normally.

Why 3: Why was the Zone 7 deviation not caught and corrected before it produced defects?

> No documented escalation threshold exists for single-zone deviations between scheduled 90-day profile verifications. Raj Patel observed the deviation but had no procedural trigger to act — the oven had passed its April 28 verification.

> Evidence: WI-SMT-014 (current rev) — confirmed by Anna Novak to contain no such threshold.

Why 4: Why did the 90-day profile verification not detect this as a risk?

> Verification is performed on a gold-board thermocouple fixture that does not place a thermocouple at the QFN ground pad — the highest thermal mass, worst-case location. A single drifting zone can remain within the verification envelope while still producing insufficient peak temperature at the joint that needs it most.

> Evidence: KIC-1913-20260428 (April 28 verification, passed); thermocouple placement map in WI-SMT-014.

Why 5: Why does the verification method not account for the worst-case joint or for paste changes that shift thermal demand?

> WI-SMT-014 was designed to confirm the oven's general thermal output against a fixed fixture — not to measure worst-case production joints, trigger re-verification on incoming material changes, or provide interim monitoring between 90-day cycles.

> Evidence: WI-SMT-014 (current rev) — confirmed by Anna Novak.

Root Cause(s)

RC-1 — Oven #1913 Zone 7 thermal deviation (co-equal contributing cause).

Mechanism: Zone 7 (peak/reflow zone) heater output drifted to ~5°C below programmed setpoint → reduced peak temperature delivered to the board at the moment of liquidus crossing → insufficient thermal energy reaching the highest-mass joint.

Verdict: PROBABLE. Strong, consistent evidence (thermocouple log, oven-to-oven contrast, timing) and the paste-alone alternative is ruled out; direct board-level confirmation at the QFN pad (Action 2, due June 12, 2026) is the step that would move this to CONFIRMED.

RC-2 — Paste lot PST-26-0339 higher liquidus (co-equal contributing cause).

Mechanism: SAC305 liquidus at 219°C (vs. 217°C standard) → +2°C higher thermal energy required for full wetting → reduced margin at the joint with the least thermal margin to begin with (QFN ground pad).

Verdict: PROBABLE. Confirmed via COA; consistent with defect isolation to the highest-thermal-mass joint; ruled out as a standalone cause because the same lot ran clean on #1911/#1912. Moves to CONFIRMED with the same Action 2 board-level profile data.

Systemic root cause — verification method escape point.

Mechanism: WI-SMT-014's 90-day gold-board verification neither instruments the worst-case joint nor triggers on paste-liquidus changes nor sets an interim zone-deviation threshold → a drifting Zone 7 heater combined with a marginally higher-liquidus paste lot went undetected until defects appeared in AOI.

Verdict: CONFIRMED — directly evidenced by WI-SMT-014 (current rev, no threshold and no QFN-pad thermocouple) and KIC-1913-20260428 (verification passed without measuring the failing location).

Ruled-Out Hypotheses

Evidence

#Evidence ItemTypeSupports
E-01Oven #1913 Zone 7 thermocouple history log (Raj Patel)Process logRC-1: Zone 7 ~5°C below setpoint, week of June 1, 2026
E-02COA — paste lot PST-26-0339Supplier documentRC-2: SAC305 liquidus 219°C; Ag 2.8%
E-03COA — standard paste lotSupplier documentBaseline: SAC305 liquidus 217°C; Ag 3.0%
E-04KIC profile verification record KIC-1913-20260428Calibration recordApril 28, 2026 verification passed; gold-board fixture; QFN pad not instrumented
E-05Thermocouple placement map, WI-SMT-014 (current rev)Work instructionConfirms gold-board-only placement; QFN pad not measured
E-06WI-SMT-014 (current rev), full documentWork instructionConfirms no interim zone-deviation threshold; no paste-change re-verification requirement
E-07AOI records — Oven #1913 output, June 2–10Inspection data84/2,000 QFN joints defective (4.2%)
E-08AOI/X-ray records — Ovens #1911/#1912, same windowInspection data6/2,000 QFN joints defective (0.3%) — normal; same paste lot
E-09X-ray confirmation — 84 defective jointsInspection dataCold joint / insufficient wetting morphology confirmed; not voiding or HiP
E-10X-ray re-inspection — 84 reworked jointsInspection dataRework confirmed conforming
E-11Run records — paste lot PST-26-0339 across all three ovensProcess logSame lot ran on all three ovens — falsifies paste-only hypothesis
E-12Customer complaint queue reviewQuality recordNo escapes; no complaints as of June 10, 2026
E-13NCR#26-0244 traceability packageQuality recordPaste lots, board lots, oven profile changes, last 8 days

Immediate Correction

#ActionDetailOwnerTarget Date
1Repair / recalibrate Oven #1913 Zone 7Restore Zone 7 heater to within ±2°C of programmed setpoint; confirm via thermocouple log post-repairRaj PatelJune 11, 2026
2Board-level profile validation at QFN-48 ground padRun board-level thermocouple profile with measurement point at the QFN-48 ground pad on BCN-IoT-4800 Rev C; confirm peak temp and TAL meet wetting requirements against PST-26-0339 liquidus (219°C); adjust profile if needed; document resultRaj Patel / Anna NovakJune 12, 2026
3Re-verification and return to serviceOven #1913 does not resume BCN-IoT-4800 Rev C production until Actions 1 and 2 are complete, documented, and Anna Novak authorizes returnRaj Patel (oven) / Anna Novak (authorization)June 13, 2026
4NCR#26-0244 closureConfirm containment complete, disposition recorded, immediate correction verified, escape point documentedAnna NovakJune 16, 2026

Escalation path: if the Zone 7 heater cannot be restored to within ±2°C of setpoint by June 11, 2026, Oven #1913 remains out of service for BCN-IoT-4800 Rev C pending equipment repair or replacement.

Approval / Sign-off

RoleNameSignatureDate
CAPA Owner / NCR AuthorAnna Novak
Reflow Oven TechRaj Patel
Quality / InspectionDan Kim
1st Shift SupervisorLinda Chen
Use-as-is disposition approvalTBD — not yet named

This report has been generated and captured here; it is not locked, closed, or signed off. Sign-off occurs through the Review & Sign-off step in the tool, where each named person above records their approval.

Escape Point

Profile verification (WI-SMT-014, 90-day cadence) does not instrument the QFN-48 ground pad — the board's worst-case thermal location — and carries no interim escalation threshold for single-zone deviations or requirement to re-verify on paste-liquidus changes. This is why a drifting Zone 7 heater and a marginally higher-liquidus paste lot combined and produced defects for several days before detection by AOI, rather than being caught at the equipment or incoming-material stage. Formal escape-point remediation (procedure revision, threshold-setting, fixture upgrade, effectiveness verification) is out of scope for this record — see Open Items & Gap Impact and route to CAPA/Full 8D if escalated.

Open Items & Gap Impact

GapWhy openImpact
No board-level reflow profile with thermocouple at the QFN ground pad from the defect windowNot available — verification method never measured this locationThe interaction cause (RC-1 + RC-2) is supported by all available indirect evidence and is physically coherent, but direct peak-temperature confirmation at the failing joint is pending. Does not change the disposition (100% X-ray screening stands regardless). Could change whether a profile adjustment alone vs. full heater repair is sufficient going forward — this is why Immediate Correction requires both (Actions 1 and 2).
Use-as-is disposition approval authority not yet named (MRB-pattern sign-off)User has not identified a role/person beyond the CAPA ownerConfidence in the formal validity of the use-as-is disposition is provisional until a named quality/engineering authority beyond Anna Novak signs it — the underlying inspection evidence (100% X-ray, passed) is not in question, but the approval-authority record is incomplete.
Paste lot PST-26-0339 continued-use decision pending Action 2 resultUser elected to defer final lot decision until board-level validation on the repaired ovenIf Action 2 validation shows insufficient margin at the QFN pad even with a repaired Zone 7, the "contributing factor, not standalone cause" framing for RC-2 would need to be revisited, and lot acceptance could change from "acceptable on verified equipment" to "requires supplier engagement."
Full preventive-action build-out (WI-SMT-014 revision, threshold definition, fixture upgrade, effectiveness verification)Explicitly out of scope for this NCMR-lite record per user directionConfidence in the disposition and immediate correction is not affected — those are scoped and evidenced. Confidence in recurrence prevention is not addressed by this record at all; if this event recurs on another oven/paste combination before a follow-on CAPA is opened, that would indicate the escape point named here needs formal closure sooner rather than later.